  1. Replacing old lighting fixtures out side (Rear) the Whistle Stop Patio and Pro-Shop to light up cart parking area and cart/walking path.

  2. Next week the cart parking area behind the Pro-Shop will be power washed and parking area will be re-painted along with berms

  3. On Monday the 27th, the concrete cart path from the parking lot to the Pro-Shop will be repaired. A large section will be replaced due to safety issue.

  4. The new Golf Carts will arrive on Monday the 27th.


137 views0 comments

Recent Posts

See All

Summary - BOD meeting February 22, 2024

Meeting called to order at 2:03 pm Reports: Chris Scott from the Activities Committee stated that they are meeting with the Restaurant to be open on the First Sunday of each Month as well as special d

Cohen Dr. Storm Water Drainage Issue

The Storm Drain on Cohen Dr. near Cayman Cir. will be repaired by April 21, 2024. The drain requires a new drain box to be installed as the old box collapsed. This issue was identified in November

Zellwood Station Center Property

In 2023 we advised the residents that Orange County had increased the property value of the center property from $2,270,620 to $10,321,000. The new established property tax for the center property is